08/27/2026
🚧✨ Quick Renovation Update 🥪❤️
We are getting closer and closer to the finish line! Our final inspection is scheduled for September 1st, and we are so excited to see everything coming together.
The progress so far:
✅ All drywall is up
✅ Mudding-sanding the compound smooth and getting walls ready with primer are complete
✅ Plumbing is completely finished
✅ Electrical is completed, with just the ceiling area waiting for inspection
✅ Once that area is inspected, we can finish covering it with drywall above the counter
And now… we’re ready to start painting! 🎨🙌
It’s been a long journey, but every day we get one step closer to opening the doors. We can’t wait to bring The Original Ricci’s Deli to the community! 🥪